Defoe Building, Hackney Community College

Client: City & Hackney NHS PCT
Value: £0.900m
Contract Period: 14 Weeks (Phased)
Form of Contract: JCT Standard:
Contract Administrator: Perkins Ogden
Quantity Surveyor: Castons
Services Engineer: DSP


Works included the strip out of existing finishes and reconfiguration of curtain walls of the existing Community College to provide new office accommodation for the City & Hackney NHS Primary Care Trust.

Project Details:-

  • Works carried out in 2 phases, North & South Block, to provide a continuous working environment for the existing occupiers and “swing space” for the fit out operations.
  • Works included the strip out of existing finishes, new M&E installation, partition walls and some ceilings.
  • Finishes included full decoration and soft floor coverings together with new doors, frames and skirtings.