The London Chest Hospital

Client: Barts & London NHS Trust
Value: £0.600m
Contract Period: 22 Weeks
Form of Contract: JCT 2 Stage D&B
Contract Administrator & QS: Castons
Architect: FDE
Services Engineer: DSP
Structural Engineer: Clancy

Works involved the construction of a new external tower landing onto the existing floor levels to provide a new emergency bed lift facility.

Project Details:-

  • Enabling works package included the removal of underground obstructions and existing services such as medical gases, mains electric, gas and drainage.
  • Construction of new lift pit and structural openings from Ground to 2nd Floor Levels.
  • New structural steel frame and rainscreen enclosure cladding
  • New lift installation and surrounding metal staircases etc.