Phases 1 and 2 Hemel Hempstead School

Works are now well underway for 2 phases of works at Hemel Hempstead School for Hertfordshire County Council.

Phase 1 consists of the demolition of the existing Science Block & Caretakers house and construction of a new 2 storey mixed use block housing, science, music and general teaching facilities with completion in October 2018.

Phase 2 consists of the demolition of the existing gymnasium & changing rooms and provision of a new Sport England sized Sports Hall along with associated spaces and changing rooms. Due to the restricted access of this phase the demolition stage was carried out over the summer shutdown period in 2018 with completion scheduled for March 2019.

Both phases have been procured under a single stage D & B route with a combined value of £5.4m.